Utility Room Renovation Costs
Scope of Works
Site survey & design sign‑off – measure space, confirm appliance list, plan plumbing / electrical routes.
Safe strip‑out of old cabinets, appliances, flooring and wall tiles; cap services.
First‑fix plumbing & electrics – reposition wastes, hot/cold feeds, add RCD‑protected circuits, extractor fan duct.
Minor building works – studwork or pocket door, patch plaster, install insulation if external wall exposed.
Floor & wall prep – levelling compound, tile backer boards or LVT underlay; prime and tank wet zones.
Fit new units, worktop & sink; connect washer, dryer, dishwasher, water‑softener as specified.
Second‑fix electrics & silicone seal; test GFCI/RCD function, commission appliances.
Decoration & snag‑out – paint, seal edges, fit splashbacks, label isolation valves; final clean‑down and hand‑over.
Typical Cost (inc. VAT)
Charge type | Low £ | High £ | Notes |
Call‑out / minimum | 80 | 150 | Design/survey visit – average emergency call‑out sits ~£110 Checkatrade |
Labour per hour | 35 | 60 | Builder hourly ≈ £50; plumber £40–£60 CheckatradeCheckatrade |
Materials | 2,000 | 6,000 | Flat‑pack units from £1 k; bespoke cabinets start £4 k+; mid‑range appliances £350–£600 each HomebuildingLivingetc |
Disposal | 190 | 320 | 6–8 yd builder’s skip inc. permit (2025 rates) Checkatrade |
Extras (electrics, UFH, structural) | 500 | 2,500 | Extra sockets £500; wet UFH £850–£1 k; small steel lintel, building‑regs fees, etc. Homebuilding |
TOTAL (most jobs come in here) | 4,000 | 12,000 | Typical 6–10 m² refit, mid‑spec finishes – low‑end £3–5 k, high‑spec £7.5–15 k How Much It CostLivingetc |
Time on Site
Basic refresh: 5 – 7 working days (cabinets & appliances in original positions).
Full re‑layout: 10 – 15 working days, allowing for plaster/tiling dry times and templated worktops.
Add time for bespoke cabinetry (manufacture gap), delayed appliance deliveries, or building‑control inspections.
Questions to Ask Your Trade
Which trade carries the CDM/Principal Contractor role and provides building‑regs sign‑off?
Will you supply and evidence Part P electrical certificates and pressure‑test new pipework?
How is moisture control handled – dedicated extractor fan, vapour‑barrier paint, UFH drying schedule?
Are cabinets and worktops factory‑finished or site‑painted, and what warranty applies?
Skip size and waste classification – can you show your waste‑carrier licence and weighbridge ticket?
What allowances are made for lead‑time items (worktops, bespoke doors) and who bears re‑visit costs?
Will weekend or evening working incur premiums and how are overruns charged (day‑rate vs. fixed)?
How to Avoid Surprises
Access & parking: book space for a 7.5‑tonne skip lorry and trades vans near the door.
Service isolation: know where mains stop‑cock and consumer‑unit are before strip‑out starts.
Ventilation & drying: keep room above 15 °C for paint/adhesive cure; run dehumidifier if advised.
Appliance spec lock‑in: order white goods before first‑fix so plumbing & electrics land in the right spots.
Permits & regs: confirm if extractor ducting penetrates an external wall (planning in conservation areas).
Variation log: insist every change is costed and signed before work continues.